Dallas North Tollway (DNT)

TollTag Logo

Dallas North Tollway (DNT)

The Dallas North Tollway is a quick, safe and convenient connection for drivers between downtown Dallas and W. First Street in Prosper. The 33-mile road crosses through the cities of Dallas, Highland Park, University Park, Addison, Farmers Branch, Plano, Frisco and Prosper. 

The first section of the tollway opened to traffic in June 1968 between downtown Dallas and Interstate 635 (LBJ Freeway). It was extended north to Briargrove Lane (just south of Frankford Road) in 1987 and to Legacy Drive in Plano in 1994. A 1.5-mile extension opened in 2004 up to Gaylord Parkway in Frisco, and an extension to US 380 opened in September 2007. In 2023, the bridges extending the DNT over US 380 into Prosper opened to travel.

NTTA will continue to extend the tollway to new destinations as the region’s northern communities continue to grow. The proposed Phase 4 extension will run nearly 14 miles from US 380 to the Collin/Grayson county line. 

Learn about the latest DNT improvement projects. Learn more about its current and future extension toward the Grayson County line (DNT Phase 4 project).

TollTag Logo

Dallas North Tollway (DNT) Widening in Frisco

The Dallas North Tollway (DNT) is being widened between the Sam Rayburn Tollway (SRT) and US 380 to accommodate population growth in the area and improve access to business and entertainment venues. This project will add an additional lane in each direction and help traffic flow as population growth continues in northern Collin and Denton counties.

Along with widening the DNT mainlanes, the project team will reconstruct the intersection and DNT bridge over Fields Pkwy in Frisco.

Opening date: Late 2025.

Placing concrete for deck pour
Drainage installation
Concrete column construction
Beams placed overnight for fourth lane expansion
Reconstruction of DNT over Fields Pkwy.
Concrete placement for column foundation.

Project Sections

Scope

SRT to US 380

Addition of a fourth lane in each direction

Recent Progress

•    Reconstruction of the northbound DNT bridge over Field Pkwy. was completed. On May 30, 2024, all traffic was shifted to the new northbound bridge. The southbound bridge over Fields Pkwy. was demolished on May 31, 2024. The north- and southbound lanes will continue to be narrowed to two lanes during bridge reconstruction.
•    Excavation and drainage installation is ongoing in the center median.
•    Widening work is underway at various intersections throughout the project area. 
•    Underpass illumination removal and installation of new illumination throughout project area is underway.

What's Next?

•    Widening work at various intersections will continue. 
•    Reconstruction of the southbound DNT bridge at Fields Pkwy. will begin. 
•    Installation of new illumination throughout project area will continue.
•    Reconstruction of the southbound John Hickman/Warren Pkwy./Gaylord Pkwy. exit ramp will begin in summer.

Project Information

Email: @email
Public Involvement: (469) 608-6880
Subscribe For Updates

TollTag Logo

DNT Phase 4 Project

The Dallas North Tollway (DNT) Phase 4 project will extend the tollway 13.7 miles north of US 380. When this extension is complete, it will provide a direct link between downtown Dallas and the growing communities in Collin and Denton counties.

Opening dates:
Phase 4A: Fall 2027
Phase 4B: To be determined.

Crews excavating to make room for the DNT in Celina
North- and southbound Dallas Pkwy. through Celina
Dallas Pkwy. where the future DNT 4A construction will begin.
Staff speaking with residents at Celina Oktoberfest.

Project Sections

Scope

Phase 4A

US 380 to FM 428, including DNT extension over US 380

Phase 4B Frontage Road

Two-lane frontage road from FM 428 to Grayson County line

Phase 4B Mainlanes

FM 428 to Grayson County line

Proposed Grayson County Tollway

A Grayson County Regional Mobility Authority project that could extend the toll road into Grayson County (not an NTTA project)

Recent Progress

•    Phase 4A:  Construction of the mainlanes from First St. to FM 428 began on April 29, 2024.
•    Phase 4A: Earthwork, drainage work, and wall preparation is underway.

What's Next?

•    Phase 4A: Construction of the mainlanes will continue with earthwork, installation of drainage materials and foundation work. 
•    Phase 4A: Coordination with stakeholders and partners continues.

Project Information

Email: @email
Public Involvement: (469) 608-6880
Subscribe For Updates

DNT 4A Map

Top Top Arrow Up